You don't have javascript enabled. Good luck with that.
Pencarian
Pembangunan Waduk Cimanggis Sudah 20 Persen
.
photo Istimewa - Beritajakarta.id

Cimanggis Reservoir Construction Reaches 20 Percent

Cimanggis Reservoir construction progress, Cibubur, Ciracas, East Jakarta recently already has reached 20 percent.

Now we focus on wet sectional area. Overall construction has reached around 20 percent

Jakarta Water Resources Dept.'s East Flow Field Head, Ahmad Syaiful, said the construction has been started since 2 months ago. There are 5 units of excavator deployed daily to dredge the site.

"Now we focus on wet sectional area. Overall construction has reached around 20 percent," he said, Thursday (3/9).

Setu Reservoir Proposed to Be Tourism Site

He explained that this reservoir will be equipped with water gates, spill way, connecting channel, and inspection road. Hopefully, the construction will be finished in November.

"Right now, all lands have been bought. Hopefully, can be finished as target," he closed.

Linked News
Popular News indeks
  1. MSMEs Bazaar Held at Binus Anggrek Campus

    access_time30-10-2024 remove_red_eye968 personTP Moan Simanjuntak
  2. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye783 personBudhi Firmansyah Surapati
  3. W. Jakarta SDA Constructs Channel on Jalan Nurul Muslimin I Kembangan

    access_time04-11-2024 remove_red_eye746 personTP Moan Simanjuntak
  4. 18 School Principals Participate in Public Agency E-Monev Presentation

    access_time02-11-2024 remove_red_eye451 personFolmer
  5. South Jakarta City Government Accelerates Stop BABS

    access_time31-10-2024 remove_red_eye414 personTiyo Surya Sakti