You don't have javascript enabled. Good luck with that.
Pencarian
Pembangunan Waduk Cimanggis Sudah 20 Persen
.
photo Istimewa - Beritajakarta.id

Cimanggis Reservoir Construction Reaches 20 Percent

Cimanggis Reservoir construction progress, Cibubur, Ciracas, East Jakarta recently already has reached 20 percent.

Now we focus on wet sectional area. Overall construction has reached around 20 percent

Jakarta Water Resources Dept.'s East Flow Field Head, Ahmad Syaiful, said the construction has been started since 2 months ago. There are 5 units of excavator deployed daily to dredge the site.

"Now we focus on wet sectional area. Overall construction has reached around 20 percent," he said, Thursday (3/9).

Setu Reservoir Proposed to Be Tourism Site

He explained that this reservoir will be equipped with water gates, spill way, connecting channel, and inspection road. Hopefully, the construction will be finished in November.

"Right now, all lands have been bought. Hopefully, can be finished as target," he closed.

Linked News
Popular News indeks
  1. Commission D Legislator Supports Park Monitoring Optimization

    access_time20-01-2025 remove_red_eye1523 personDessy Suciati
  2. Realizing Food Self-Sufficiency, Jakarta Holds Simultaneous Planting Activity

    access_time21-01-2025 remove_red_eye943 personAldi Geri Lumban Tobing
  3. Gulkarmat to Intensify Fire Mitigation Education

    access_time22-01-2025 remove_red_eye460 personBudhi Firmansyah Surapati
  4. BMKG Warns of Potential High Rainfall in Jakarta

    access_time22-01-2025 remove_red_eye429 personDessy Suciati
  5. City and Kejati Forge Cooperation for Good Government Governance

    access_time21-01-2025 remove_red_eye412 personFolmer