Pembangunan Waduk Cimanggis Sudah 20 Persen
.
photo Istimewa - Beritajakarta.id

Cimanggis Reservoir Construction Reaches 20 Percent

Cimanggis Reservoir construction progress, Cibubur, Ciracas, East Jakarta recently already has reached 20 percent.

Now we focus on wet sectional area. Overall construction has reached around 20 percent

Jakarta Water Resources Dept.'s East Flow Field Head, Ahmad Syaiful, said the construction has been started since 2 months ago. There are 5 units of excavator deployed daily to dredge the site.

"Now we focus on wet sectional area. Overall construction has reached around 20 percent," he said, Thursday (3/9).

Setu Reservoir Proposed to Be Tourism Site

He explained that this reservoir will be equipped with water gates, spill way, connecting channel, and inspection road. Hopefully, the construction will be finished in November.

"Right now, all lands have been bought. Hopefully, can be finished as target," he closed.

Linked News
Popular News indeks
  1. Rano Inspects Location and Delivers Aid to Fire Victims in Bukit Duri

    access_time20-07-2025 remove_red_eye669 personNurito
  2. Assistance Continues to Be Provided to Bukit Duri Fire Victims

    access_time20-07-2025 remove_red_eye454 personNurito
  3. Rano Ensures Swift Action in Bukit Duri Fire Handling

    access_time19-07-2025 remove_red_eye396 personFakhrizal Fakhri
  4. C. Jakarta TP PKK Grows 2,470 Chili and Tomato Seedlings

    access_time18-07-2025 remove_red_eye389 personFolmer
  5. Munjirin Leads Simultaneous Planting at RPTRA Rawa Jaya

    access_time18-07-2025 remove_red_eye385 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik